Armington Junction bridge repair, Big Otter Creek – Cascade County, MT SPA 124 Permit Decision Notice FWP-CEA-FSH-R4-25-017
Apr 7, 2025 10:57 AM
Based on the environmental review provided in the Draft EA, and, to the greatest extent possible, in accordance with all applicable laws, rules, regulations, and policies, FWP determined the proposed action (Alternative 2), will not have significant adverse impacts on the human environment associated with the proposed action and constitutes a reasonable and appropriate strategy to achieve identified objectives. Therefore, preparation of an environmental impact statement or EIS is unnecessary.
FWP hereby adopts the Draft EA as final and approves Alternative 2, the Proposed Action of the placement of rip rap on the north-facing headwall of a bridge over Big Otter Creek to prevent erosion from high water. The current north-facing headwall is sand and a few rip rap rocks.
Related Documents