Skip to main content
Go to search page

Head Lane Bridge Replacement (Sevenmile Creek) SPA 124 Permit Decision Notice FWP-CEA-FSH-R4-24-041

Dec 2, 2024 2:37 PM

Based on the environmental review provided in the Draft EA, and, to the greatest extent possible, in accordance with all applicable laws, rules, regulations, and policies, FWP determined the proposed action (Alternative 2), will not have significant adverse impacts on the human environment associated with the proposed action and constitutes a reasonable and appropriate strategy to achieve identified objectives. Therefore, preparation of an environmental impact statement or EIS is unnecessary.

 

FWP hereby adopts the Draft EA as final and approves Alternative 2, the Proposed Action of replacing a current bridge structure on Head Lane at the Sevenmile Creek crossing.

 

Related Documents